List of Mandatory Tools and Materials

  Ceramic Tiles / Vitrified Tiles  Diamond Cutter machine, Tile Cutter, Levelling Machine , Spirit Levels, Tile  Adhesives, Table/ Stoll, Measuring Tape Steel, Trowel 8 mm , Adhesive mixing  machine, Rubber hammer, Tiles vibrator machine, approved grout powder,  sponge, holes cutting bit. 

Find out more

Ali Enterprises

Preparatory Requirements

  •  First cleaning of completed floor slab and toilet wall as wall hacking was  done.
  • Making FFL but rigid lumber at every corner of floor area (bedroom or hall  area).  
  •  Making finishing but rigid lumber at toilet dado for plumbing alignment  and to cross check right angle of every wall.
  •  Tiles marking to be done on toilet dado. 
  •  Before starting tiles work need to take the clearance from electrical,  plumbing, and tiles work related in-charge from client side. 
  •   Maintaining tiles batch number and stocking same tiles for reconciliation.  
  •  Need to take waterproofing clearance for wet area.   Follow approved drawing. 
  •   Discard any tiles that are chipped or cracked. Need to cut that tiles neatly  and accurately. 

Procedure for Tiles Flooring.

  1.   Maintaining FFL level. 
  2.   Maintain checklist documentation.   Follow Approved drawing.  
  3.  Maintaining proper tiles for proper location by name.  
  4.  Maintaining tiles batch number and stock maintaining for reconciliation in  future.   
  5.  Using proper grade adhesive in dry area and wet area.  
  6.   Dry laying to cross check wall bend or right angle problem.  
  7. Mixing adhesive with proper ration of adhesive and water.   Need to consume mixing adhesive within 30 minutes.  
  8. Fixing tiles with 8mm trowel, rubber hammer, tiles vibrator, spirit level as  mention above on thin adhesive.  
  9.  Maintain tiles arrow mark during fixing and following each tiles joint as paper  joint.  
  10.  Tiles must be correctly positioned at the time they are placed and laid with  joints.  
  11.  Maintain proper slope at wet area.  
  12.   Set out the tiling width joint of consistent width, ensuring they are horizontal  and parallel.  
  13.  Once tiles fixed immediately cleaning to be done.  
  14. Once tiles fixed no one can move on tiles.  
  15.  After completing of tiles (tiles cover, adhesive empty bag, waste tiles need to  be dump.)  
  16.   Use the approved grout and apply the grout in every joint smooth, level, and  clean application.  
  17. Once checking work is done covering with 3mm protection sheet.  

Procedure for Tiles dadoing.

  1.  Procurement team to take undertaking from the manufacturer whether  the tile is fit for flooring or wall dado  
  2.  Maintain checklist documentation.  
  3.  Follow Approved drawing.  
  4.  Maintaining proper tiles for proper location by name.  
  5.  Maintaining tiles batch number and stock maintaining for reconciliation in  future.   
  6.  Using proper grade adhesive.   
  7.  Mixing adhesive with proper ration of adhesive and water.  
  8.  Need to consume mixing adhesive within 30 minutes.  
  9.  Fixing tiles with 8mm trowel, rubber hammer, tiles vibrator, spirit level as  mention above on thin adhesive.  
  10.  Maintain tiles arrow mark during fixing and following each tiles joint as paper  joint.  
  11.  Tile marking to be given and Bull Marking to be proceed.  
  12.  Ensure MEP clearance to be taken prior to start and make sure that  pressure  testing has been done  Ensure signoff document for waterproofing activity available at site. 
  13.   If the Thickness of Adhesive above 8-10 mm for Dado should be provide  plastering from client side.  
  14. Cutting holes with round cutting bits.  
  15.  After 5 days of tiles fixing joint filling to be done with approved  grouting. 

Sorting of Tiles

  1.  Take 9 tiles and lay them in a plain area for checking each of tiles size.  
  2. Putting one tiles on other for any bends in tiles.  
  3.  Checking right angle of tiles by measuring length, breadth and diagonal.   
  4.  Tiles thickness to be check.  
  5.  Checking tiles lippage by sliding round coin.   Checking color, shade, batch number of tiles.  
  6.  Check for scratch , pinholes, bubbles,  
  7.  Checking hardener of tiles by cutting 1 tiles. (if hardener is more can’t cut tiles  in proper size )   Remove damage or faulty tiles.  
  8.  Batch wise stocking and keeping stock for reconciliation.  
  9.  Keeping all the tiles in dry area of minimum 100mm of height from ground  level.  

Surface preparation

  1.  Check surface is free of defects and ensure all the MEP works completed  and clearance shall be taken by MEP team.   All Plumbing Lines are required to be plugged with end caps before  Tiling Works.  
  2.  Ensure any electrical and Plumbing fixtures are not getting off-centre  like half at plaster wall half in tile area  
  3.  Ensure the Shower test has been done for external toilet wall surfaces. 
  4.  Check electrical and plumbing chase cuts are filled with Ready mix  plaster and fiber mesh jaali.  
  5. Check toilet waterproofing is done or not   Check water tightness carried out to ensure all tie rods, wall ties are  filled properly  
  6. Transfer 1 m level marking from lift lobby  
  7. Clean surface with fresh water and the surface shall be in SSD before  laying dado  
  8.  Check tile bull mark, right angle & uniform internal dimension  
  9.  Check thickness of adhesive for thin bed adhesive max 8-10mm.  
  10.  In case the thickness is more than 10 mm, then Ready mix plaster is  applied as backing plaster (chat coat) with hacking of min 40 Nos per  sqft on RCC surface to rectify and ensure curing for 03 days. Make sure  that the thickness of RMP plaster is maximum 15mm allowed.  
  11.  Install bottom Patti (metal Patti) horizontally on bottom layer of tile  
  12.  Install bottom layer of dado tile after completing flooring considering  the slope profile.1 meter reference level 

Installation

  1.  Mixing adhesive with proper ratio of adhesive and water as per manufacturer  guideline.  
  2.  Cleaning toilet wall with wet sponge as during hacking too much dust power  stick on wall.  
  3.  Using 8mm trowel vertical direction for tiles fixing.  
  4.  Use level machine for tiles level joint and for floor slop.  
  5.  Maintaining arrow mark of tiles.   
  6.  Using cut pies tiles for small tiles on wall or floor.  
  7.  Ensure the ledge wall top and windowsill level to be followed as per  approved drawing and make sure the level is transferred from 1M marking  level.  
  8. Top layer of dado to be marked and checked after installation in case of  false ceiling provision  

Ali Enterprises

08670271943

Copyright © 2026 Ali Enterprises  - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

Accept